Reporting a Horizon Europe project with your documentation in order

Figures taken from the Horizon Europe Model Grant Agreement (HE MGA). Always check the terms of your own agreement.

What must be reported, and when

The Horizon Europe model grant agreement provides for two kinds of reporting: (HE MGA)

  • Continuous reporting (art. 21.1): project progress (deliverables, milestones, results, critical risks and indicators) is recorded in the Continuous Reporting tool of the Funding & Tenders Portal.
  • Periodic reporting (art. 21.2): at the end of each period, a technical part using the Portal template and a financial part with financial statements and an explanation of the use of resources. The model sets the deadline at 60 days after the end of the reporting period.

When signing the financial statements, each beneficiary confirms that the declared costs can be substantiated by adequate records and supporting documents.

How long documents must be kept

Article 20 requires beneficiaries to keep records and supporting documents proving the proper implementation of the action: contracts, invoices and accounting records that reconcile what was declared with the accounts.

ObligationStandard period
Keep records5 years after final payment (3 for grants of not more than €60,000)
Reviews and auditsUp to 2 years after final payment
Certificate on financial statementsOnly at final payment, if the beneficiary's requested contribution reaches €430,000

In addition, the Commission, OLAF, the European Court of Auditors and the European Public Prosecutor's Office may carry out checks, audits and investigations (art. 25).

For other directly managed EU programmes, the general agreement sets the same 5 years (3 up to €60,000). For Erasmus+ managed by national agencies, national agreements apply: check yours.

Where it gets complicated in a consortium

  • Each partner documents in its own way and language.
  • Deliverables are sent by email and nobody knows which version is final.
  • Work-plan responsibilities are not reflected in day-to-day work.
  • Five years after final payment, whoever prepared the report has moved on.

How to be ready

1. A shared space from month one

Tasks, deliverables and documents from all partners in the same place, following the work plan structure.

2. Every document linked to its deliverable or milestone

The technical report is then built from what already exists.

3. Visible owners and dates

Each deliverable with its owner, due date and status.

4. Think about the audit from the start

Keep the supporting documents the financial part will need in the same space, with a structure that will still make sense five years later.

How Universitas Technology can help

We build digital platforms for research projects. We start with one part of the project and its real partners, and extend to the rest if it works. Behind it is UNIVERSITAS's experience in research management and European projects, as coordinator and as partner.

Book 30 minutes to see how it would fit your project.

Shall we talk for 30 minutes?